A-Grade office & retail space in prime Newcastle CBD location. Construction commenced August 2020, and completion early 2022.
Macquarie Tower
Hunter Precast delivered a total of 741 precast panels for the Macquarie Tower project, covering 7,744m² across facades, cores, balustrades, and columns.
Panel Breakdown
- Facades: 220 panels | 3,630m²
- Cores: 132 panels | 2,083m²
- Balustrades: 93 panels | 358m²
- Columns: 296 panels | 1,673m²
Installation
- 38 installation campaigns
- First install: 7 Sept 2023
- Final install: 7 Dec 2024
Materials & Resources
- Concrete: 1,615m³ (≈ 3,960 tonnes)
- Reinforcement cages: 254 tonnes
- Stock bar usage: 48.6 km
- Grout: 42 pallets (48 bags each), installed entirely by hand